On approving the Yerevan Urban Development Regulations
The Urban Development Charter of Yerevan has been approved. The organization and responsibility for the implementation of the decision have been assigned to S. Danielyan, Chief Architect of Yerevan, and K. Davtyan, Deputy Mayor of Yerevan. The Mayor of Yerevan supervises the implementation of the decision.
What was decided
- Document approvedMunicipal act
Approve the Urban Development Charter of Yerevan (annex).
- Oversight assignedMunicipal act
Assign the organization and responsibility for the implementation of this decision to S. Danielyan, Chief Architect of Yerevan, and K. Davtyan, Deputy Mayor of Yerevan.
- Oversight: S. Danielyan
- Oversight: K. Davtyan
- Oversight assignedMunicipal act
Control over the execution of the decision is carried out by the Mayor of Yerevan.
- Oversight: YE. ZAKHARYAN
Full text
REPUBLIC OF ARMENIA
MAYOR OF YEREVAN
DECISION
N 2228-A December 19, 2006
ON APPROVING THE YEREVAN URBAN DEVELOPMENT CHARTER
Guided by Article 37, Part 1, Point 2 and Article 85, Part 1 of the RA Law "On Local Self-Government":
1. To approve the Yerevan Urban Development Charter (Appendix).
2. To assign the organization and responsibility for the implementation of this decision to S. Danielyan, Chief Architect of Yerevan, and K. Davtyan, Deputy Mayor of Yerevan.
3. The Mayor of Yerevan shall supervise the implementation of the decision.
MAYOR OF YEREVAN YE. ZAKHARYAN
YEREVAN URBAN DEVELOPMENT CHARTER
In accordance with the urban development and land legislation and other legal acts of the Republic of Armenia, this charter defines the procedures for carrying out urban development activities in the city of Yerevan, the competencies and obligations of Yerevan City Hall, as well as of urban development entities (developers, project designers, and construction implementers).
CHAPTER 1
LAND USE CONDITIONS AND LAND ALLOCATION PROCEDURES
SECTION 1. GENERAL PROVISIONS
1. The intended and functional purposes of lands in the city of Yerevan are defined by the Yerevan Master Plan.
2. The permitted use of land plots is defined based on the Yerevan Master Plan, land zoning and use schemes, and other normative legal acts.
3. Land plots are allocated taking into account their intended and functional purpose, with an indication of permitted use:
- without public bidding
- by competition (auction)
4. The land user is obliged to ensure the state registration of their rights to the land plot.
SECTION 2. PROCEDURE FOR GRANTING LAND WITHOUT PUBLIC AUCTION
5. State-owned land plots are granted without tender (auction) in cases provided for by the Land Code of the Republic of Armenia and by the procedure approved by the Government of the Republic of Armenia's Decision No. 286 of 12.04.2001 "On Approving the Procedure for the Use, Development Right, and Granting of Use of State and Community-Owned Land Plots" (hereinafter referred to as the Procedure).
6. The issue of granting a land plot is considered based on an application addressed to the Mayor of Yerevan by a natural or legal person.
7. The application is processed in accordance with the Yerevan City Hall's record-keeping procedure, based on the "one-window" principle (Mayor of Yerevan's Decision No. 2385-A of 15.12.04, "On Approving the Record-Keeping Procedure of Yerevan City Hall and Establishing a Working Group to Exercise Necessary Control over the Process of Implementing the 'One-Window' Principle").
8. The application must be accompanied by the documents specified in the appendix to these regulations.
9. In the absence of the necessary documents, applications are returned within a three-day period through the authorized working group, stating the reasons and grounds for the return of the applications.
10. The deadline for adopting a decision on granting a land plot and issuing the land plot plan is 45 days.
11. The conclusion on granting a land plot is provided by the Architecture and Urban Development Department of the Yerevan City Hall Staff.
12. The site inspection of the land plot, the refinement of the topographic survey, the preparation of planning schemes, as well as the issuance of the master plan after the adoption of the Mayor of Yerevan's decision on granting the land plot, is a paid service and is carried out by "Urban Development" state CJSC at the expense of the applicant.
In cases of refusal to pay for the mentioned works, the consideration of the issue is terminated.
13. After determining the boundaries of the land plot, and preparing the land plot's plan and description, a land plot provision file is compiled at "Urban Development" CJSC based on the mentioned documents, which is submitted to the authorized department for the preparation of the Mayor's draft decision.
14. The land plot provision file includes:
a) Application,
b) Conclusion and report of the Department of Architecture and Urban Development,
c) Land plot plan,
d) Land plot description,
e) Copy of the passport of the individual, copy of the state registration certificate of the legal entity (organization).
f) Other documents related to the case.
The land plot provision file is compiled in 1 copy.
15. Based on the land plot provision file, the authorized department of the Yerevan City Hall staff prepares the draft decision of the Mayor of Yerevan.
16. After the adoption of the Mayor of Yerevan's decision on the provision of the land plot, the draft decision, with all necessary annotations, the grounds for the draft, including the land plot provision file, are kept in the protocol division of the City Hall staff.
17. After receiving the decision on the provision of the land plot and the master plan, the applicant concludes a land plot lease (alienation) agreement with the body authorized by the Mayor of Yerevan (head of the respective district community) or the department (authorized department of the Yerevan City Hall staff).
18. The obligation for state registration of the land plot in accordance with the procedure established by the legislation of the Republic of Armenia is borne by the land user (individual or legal entity) defined by the decision of the Mayor of Yerevan.
SECTION 3. PROVISION OF A LAND PLOT THROUGH COMPETITION (AUCTION)
19. In the city of Yerevan, land plots constituting state property are provided with the right of lease or development through a tender process and are alienated through an auction process based on the decision of the Mayor of Yerevan on announcing a tender (auction), guided by Articles 48, 61, 67 - 70, 77 - 80 of the RA Land 1 Code, Articles 463 – 465 of the RA Civil Code, the RA Law "On Public Auctions" and points 22-28 and 43- 59 of the RA Government Decision No. 286 of April 12, 2001, "On approving the procedure for the provision of state and community land plots in a new edition".
20. The organizational works for providing land plots with the right of lease or development through tender and alienating them through auction are carried out by the following bodies created by the decision of the Mayor of Yerevan:
a/ the tender and auction commission
b/ the commission for the selection of land plots and urban development programming.
21. The procedure for organizing and conducting tenders and auctions is defined by the Decision of the Mayor of Yerevan No. 375-A of 17.03.2006 "On the regulation of organizing and conducting public auctions /tenders and auctions/ of land plots constituting state property within the administrative boundaries of the city of Yerevan" /appendix/.
SECTION 4. THE PROCEDURE FOR RESTORING THE GROUNDS FOR LAND ALLOCATION
22. According to point 6 of Article 118 of the RA Land Code, the process of restoring the grounds for land allocation is initiated based on the application of the interested legal entity addressed to the Mayor of Yerevan.
23. Through the procedure for restoring the grounds for land allocation, the applicant is provided with the land plot occupied by buildings constructed in accordance with the requirements of the law and legal acts and necessary for their maintenance, which (or a part of it) cannot be provided as a separate property unit through public auctions.
24. The documents provided for by the appendix of this charter are attached to the application.
25. A legal expert opinion on the merits of the application is provided by the Legal Department of the Yerevan City Hall Staff.
If the application is not substantiated, the applicant is provided with a corresponding written clarification.
26. Based on the conclusion of the Legal Department, the further course of consideration of the application is regulated by the rules of "Procedure for Granting Land Without Competition (Auction)" in Chapter 1 of this Charter.
CHAPTER 2
PROCEDURE FOR FORMULATING ARCHITECTURAL AND CONSTRUCTION DOCUMENTS
SECTION 5. PROCEDURE FOR ISSUING ARCHITECTURAL AND PLANNING ASSIGNMENTS
1
27. In accordance with Articles 17 and 26 of the RA Law "On Urban Development" and the procedure approved by RA Government Decision No. 1473-N of 29.08.02 "On Approving the Procedure for Issuing Architectural and Planning Assignments", the Architectural and Planning Assignment in Yerevan is issued by the Mayor of Yerevan or his duly authorized deputy or the Chief Architect of Yerevan.
28. In the territory of a Yerevan district community, this authority is exercised by the head of the district community, with respect to the following objects:
a) reconstruction of an individual residential house on a land plot owned by right of ownership (if, as a result of the reconstruction, it does not exceed three floors and a mansard) and its auxiliary buildings;
b) internal planning changes in multi-apartment buildings requiring a construction permit for common use areas (except in cases of changes in their functional purpose), as well as opening windows to ensure necessary lighting.
29. To receive an assignment, the developer submits an application to the Architecture and Urban Development Department of the Yerevan City Hall Staff (to the head of the respective community).
(the form approved by RA Government Decree No. 1473-N of 29.08.02 is to be filled in).
30. The application shall be accompanied by the documents provided for in the appendix to these regulations.
31. An application for obtaining a task for developing a project for constructing an additional floor (including a mansard), an annex, or other improvement or alteration in an existing building must include a professional opinion on the stability, strength, and reliability of the building, issued by a research or design organization with appropriate authorizations, relevant sketches revealing the principles of the project, the written consent of the building's author in cases provided for by the RA Law "On Copyright and Related Rights," as well as the written consent of the other owners of the building in the manner provided for by the RA Law "On the Management of Multi-Apartment Buildings."
32. An application for obtaining a task for developing a project for altering property that is an immovable monument of history and culture shall be accompanied by the consent or professional opinion of the state authorized body, as provided for by the RA Law "On the Preservation of Immovable Monuments of History and Culture and the Historical Environment" (Article 9, point "ja").
33. The competent body shall, within 20 days from the date of submitting the application, issue a task to the developer or reject it, stating the reasons for rejection.
34. The developer may make appropriate changes to the rejected application and the submitted documents and resubmit the application to the competent body.
35. The competent body shall review the resubmitted application and issue a task to the developer within 10 days.
36. The rejection of an application may be appealed in court.
SECTION 6. APPROVAL OF PROJECTS FOR THE CONSTRUCTION AND RECONSTRUCTION OF BUILDINGS AND STRUCTURES
37. Designs for residential, public, and industrial buildings and structures requiring a construction permit under the legislation of the RA are coordinated in the city of Yerevan by the Chief Architect of Yerevan, as well as 1 in cases defined by Article 26 of the RA Law "On Urban Development" — by the head of the corresponding district community.
38. The design submitted for coordination shall be accompanied by the expert examination conclusion carried out in accordance with the law and the RA Government Decision No. 96 of 02.02.02 "On Approving the Procedure for the Expert Examination of Urban Development Documents" (except for designs issued with the written guarantee of the designer in defined cases and manner).
39. According to Article 13 of the RA Law "On Environmental Impact Expertise," in defined cases, the developer is obliged to ensure the conduct of a state environmental expert examination of the planned activity, submitting a corresponding conclusion on preventing and mitigating impacts on the surrounding natural environment.
40. In the package of the design submitted for coordination, along with the schedule for the execution of construction works, the scheme for the organization of the construction site must also be submitted.
41. Design documents are coordinated within a 10-day period from the date of their submission, and in cases of public notification — within a 21-day period. For the coordination of design documents returned with comments, the specified period is calculated within a 5-day period from the date of their re-submission.
SECTION 7. PROCEDURE FOR THE PLACEMENT OF NON-PERMANENT STRUCTURES
42. The allocation of a land plot for the purpose of placing non-permanent structures and the registration of rights to the land is carried out by the RA Government Decision No. 286 of 12.04.01 "On Approving the Procedure for Granting the Right of Use, Construction, and Provision of Use of Land Plots Being State and Community Property" in the established order and by the rules of the "Procedure for providing land without public auction" of this Charter.
43. An architectural-planning assignment is not issued for the design of non-permanent structures. Design documents are developed on the basis of the decision on the provision of the land plot, which fixes the spatial dimensions of the structures, the conditions for their placement on the land plot, and the requirements presented for architectural solutions, based on the specifics of the terrain and (or) the object.
SECTION 8. PROCEDURE FOR CHANGING THE FUNCTIONAL PURPOSE OF BUILDINGS, STRUCTURES OR A SECTION THEREOF
44. When changing the functional purpose of buildings and structures, the owner of the given structure or a person endowed with relevant powers acts as the customer.
45. The change of the functional purpose of a building, structure or a section thereof is carried out according to the procedure established by the Republic of Armenia Government Decision No. 88 of 02.02.02 "On approving the procedure for changing the functional purpose of buildings, structures or a section thereof in the Republic of Armenia," based on the customer's application, by a project developed, coordinated and approved in accordance with the architectural-planning assignment issued by the Mayor of Yerevan (except for cases established by the legislation of the Republic of Armenia for which a construction permit is not required).
CHAPTER 3 RIGHTS AND OBLIGATIONS OF SUBJECTS OF URBAN DEVELOPMENT ACTIVITY
SECTION 9.ԿԱՌՈՒՑԱՊԱՏՈՂԻ RIGHTS AND OBLIGATIONS
46. A user who is the owner of real estate or is endowed with the right to change it acts as a developer when carrying out urban development activities.
The rights, obligations, and responsibilities of the developer are regulated by the Land Code of the Republic of Armenia, the Civil Code of the Republic of Armenia, the Code of Administrative Offenses of the Republic of Armenia, the Law of the Republic of Armenia "On Urban Development," and other legal documents.
47. To ensure environmental safety, sanitary protection, and the preservation of developed lands when carrying out construction in Yerevan, the developer is obliged to comply with the following rules within the framework of civil-legal relations with Yerevan City Hall:
a/ The project package submitted for approval must mandatorily include a construction site organization scheme along with the construction work schedule.
b/ When submitting an application for a construction permit, the developer or the entity carrying out demolition work is obliged to conclude an agreement with the "Yerevan Investment Programs Implementation Office" SNCO regarding the transportation of construction waste and soil fill to the designated landfill.
c/ Construction work on the facilities under construction may only begin after the construction site has been fenced off with temporary barrier structures.
The surfaces separating construction sites may be used to display necessary information about the construction, as well as temporary advertisements, in the prescribed manner.
d/ When carrying out construction on land plots adjacent to streets, temporarily equip sidewalks with platforms, railings, and covers necessary to ensure safe pedestrian movement.
e/ In accordance with the procedure established by the Government of the Republic of Armenia's Decision No. 1622-N of 19.09.2002 "On Approving the Procedure for the Use of the Fertile Soil Layer," the developer is obliged to carry out the removal, preservation, and use of the fertile soil layer.
f/ The entity carrying out construction in the administrative territory of Yerevan is obliged to install a signboard at the construction site before commencing construction work, which will include the following information about the facility under construction: the following information necessary for urban development and land control regarding the (reconstructed) object:
- name and purpose of the object, - number and date of the relevant decision of the Mayor of Yerevan, - area of the allocated land plot, - area and number of floors of the object under construction, - data of the developer (customer), - data of the contractor and state license number, - number and date of the construction permit, - data of the author (architect) of the architectural and construction design, - start and end dates of construction, - sketch color image of the object under construction.
SECTION 10.ՔԱՂԱՔԱՇԻՆԱԿԱՆ RIGHTS AND OBLIGATIONS OF DEVELOPERS OF URBAN DEVELOPMENT DOCUMENTS AND ENTITIES CARRYING OUT CONSTRUCTION
48. The rights and obligations of developers of urban development documents and entities carrying out construction are defined and regulated by the Civil Code of the RA, the RA Laws "On Urban Development", "On Copyright and Related Rights" and other legal acts.
49. The responsibility of developers of urban development documents and entities carrying out construction is regulated by the RA Code "On Administrative Offenses" and other legal acts.
CHAPTER 4 PROCEDURE FOR INFORMING ABOUT PLANNED CHANGES IN THE VITAL ACTIVITY ENVIRONMENT IN YEREVAN CITY AND FOR THE PARTICIPATION OF REPRESENTATIVES OF THE PUBLIC IN THE DISCUSSION OF PUBLISHED URBAN DEVELOPMENT PROGRAMS AND DESIGNS AND IN THE ADOPTION OF DECISIONS
50. The participation of public representatives in informing about planned changes in the living environment in Yerevan, in discussing published urban development programs and projects, and in making decisions, is carried out in accordance with Articles 12-14 of the Law of the Republic of Armenia "On Urban Development", the decision of the Government of the Republic of Armenia dated 28.10.1998, No. 660 "On approving the procedure for informing about planned changes in the living environment and for the participation of public representatives in discussing published urban development programs and projects and in making decisions", and this procedure.
51. The Mayor of Yerevan informs the public about planned changes in the living environment within the territory of Yerevan.
52. Information is provided through:
a) mass media (local and public radio, television, newspaper)
b) events for displaying programs and projects, publications
c) public discussions
d) mandatory publication of information in the "Yerevan. 7 Days" newspaper.
53. For the discussion of projects for buildings and structures being constructed in the territory of Yerevan, informing public representatives is carried out at the stage of agreeing on the sketch project provided by the architectural and planning assignment, by the developer (client), at their own expense, by installing a display panel at the planned construction site, as well as through mass media and other means, ensuring broad public discussions if necessary.
54. The developer pre-agrees the appearance and content of the panel of the established form with the Architecture and Urban Development Department of the Yerevan City Hall Staff.
55. The deadline for the publication and display of urban development programs and projects is set at 15 days.
56. Representatives of the public shall submit their observations and proposals, substantiated by normative and other legal acts, as well as conclusions of independent expert examinations carried out at their own expense regarding the published drafts, in writing to the Architecture and Urban Development Department of the Yerevan City Hall Staff within the prescribed period.
57. After studying and analyzing the observations and proposals with the participation of public representatives (authors of observations and proposals), the Architecture and Urban Development Department of the Yerevan City Hall Staff shall adopt one of the following 3 decisions within a 3-day period:
a/ approves the sketch design, with a written instruction to make appropriate changes if necessary.
b/ rejects the approval of the design with a written justification.
c/ submits a draft of the corresponding decision to the Mayor of Yerevan regarding the change of the target designation of construction or the permitted use of the land plot.
CHAPTER 5 SECTION 11. PROCEDURE FOR ISSUING CONSTRUCTION PERMITS AND DEMOLITION PERMITS
58. A construction permit is a document that confirms the developer's right to carry out any construction activity both in newly developed areas and in existing buildings and structures.
59. A demolition permit is a document that confirms the owner's right to demolish buildings and structures.
60. Only current repair and interior finishing works, as well as landscaping works, may be carried out without a construction permit, if they do not hinder the target use of the immovable property and/or do not contradict the established servitudes.
61. Any construction and parallel work based on a permit may be carried out exclusively within the boundaries of the area determined by the design.
62. The permit for construction (demolition) in Yerevan is issued by the Mayor of Yerevan in accordance with the procedure established by the Law of the Republic of Armenia "On Urban Development" and the Decision of the Government of the Republic of Armenia No. 91 dated 02.02.02 "On Approving the Procedure for Construction Permits and Demolition Permits in the Republic of Armenia".
63. The authority vested in the Mayor of Yerevan may be transferred by a decision of the Mayor of Yerevan to the relevant deputy or the Chief Architect of Yerevan.
1
64. In cases defined by Article 26 of the Law of the Republic of Armenia "On Urban Development", the authority to issue construction permits vested in the Mayor of Yerevan within the territory of a Yerevan district community is exercised by the head of the respective district community for the following objects:
a/ reconstruction of an individual residential house on a land plot owned by right of ownership (if, as a result of the reconstruction, it does not exceed three floors and a mansard) and its auxiliary structures.
b/ internal layout changes in multi-apartment buildings requiring a construction permit for common use areas (except in cases of changes in their functional purpose), as well as opening of windows for the purpose of ensuring necessary lighting.
65. The construction permit is issued by the body that provided the architectural and planning assignment, after the architectural and construction design documents are agreed upon in the manner prescribed by the Government of the Republic of Armenia and approved by the developer, for the period specified in point "J" of part 4 of Article 6 of the Law of the Republic of Armenia "On Urban Development".
66. If the construction (except for individual residential houses) is not completed within the terms calculated according to the norms of construction duration for buildings and structures for the given urban development activity and specified in the construction permit, the body issuing the construction permit shall send a written warning to the developer to extend the term specified in the construction permit and complete the construction within that term or the urban development activity belonging to him by right of ownership the alienation of the object. Moreover, the duration of construction may be extended by the body issuing the construction permit by no more than the period calculated according to the norms for the duration of construction for the uncompleted works of the given object.
67. In case of non-compliance with the specified requirement, the developer shall be subjected to administrative liability by the body issuing the construction permit in the manner prescribed by law.
68. If, within one month after receiving the warning, the developer does not apply to the body issuing the construction permit with an application to extend the construction period, or does not complete the construction within the new period specified by the construction permit, or does not alienate the object belonging to him by right of ownership, then the body issuing the construction permit shall again subject him to administrative liability and apply to the court with a claim to sell the given object, in the manner and at the price determined by the court, but not less than 75% of the cadastral value of the object.
69. The construction permit is issued simultaneously with the approval of the architectural and construction design documents for the given object, and the design documents are considered approved if the developer does not submit a written objection regarding their approval to the approving body.
70. In the city of Yerevan, the local fee prescribed by law for a construction (demolition) permit is paid to the budget of the respective district community according to the location of the object.
71. The types of permits are: a/ permit for the construction of new objects, buildings and structures, and for the performance of construction and installation works, b/ permit for the reconstruction, strengthening, restoration works of existing objects, c/ permit for the demolition of existing objects.
72. To obtain a construction permit, the developer submits the following documents to the competent body issuing the permit: a/ application (Form N1 approved by RA Government Decision No. 91 of 02.02.02),
b/ for the construction of the object: the design documents approved in the prescribed manner, which indicate the duration of the construction, and in the case of a project developed in stages, the design documents of the intermediate approved stage.
73. The application shall state: a/ the purpose (nature) and address of the object, b/ in cases prescribed by law, the economic entities that developed the design documents of the object and conducted an expert examination in the prescribed manner, with the numbers of their licenses for carrying out the relevant activity, and in cases prescribed by the legislation of the Republic of Armenia, the contractor's guarantee for design works.
74. The application shall be accompanied by the contract concluded with the "Yerevan Construction Investment Programs Implementation Office" state non-commercial organization regarding the transportation of construction waste and soil fill to the appropriate landfill allocated for them.
75. Developers are obliged to carry out construction in accordance with the approved architectural and construction project, the legislation of the Republic of Armenia, and the requirements of normative and technical documents.
76. The owner or a person authorized by him in the prescribed manner shall submit the following documents to the competent authority issuing the demolition permit: a/ an application (Form N2 approved by Decision No. 91 of the Government of the Republic of Armenia dated 02.02.02), b/ a copy of the certificate of registration of ownership rights to the immovable property and a power of attorney issued by the owner in the prescribed manner (if the application is submitted by an authorized person).
77. The application shall state: a/ the purpose (nature) and address of the object to be demolished, b/ the purpose of demolition, c/ the main indicators of the object to be demolished.
78. The competent authority issuing the permit shall review the documents submitted by the developer (owner) and make a decision on granting or refusing the permit within no more than 5 days from the date of submission of the application.
79. Construction and demolition permits are issued in accordance with the forms approved by the Government of the Republic of Armenia (Forms N3 and N4).
80. Along with the construction permit, the developer is provided with a construction logbook, which is stamped by the competent authority issuing the permit.
81. If the construction of a newly built object cannot be carried out without the demolition of an existing object (objects), then the construction permit issued to the owner, with a corresponding note, also serves as a demolition permit.
82. The actual demolition of the object and new construction are carried out after obtaining the construction permit, in the sequence defined by the architectural and planning assignment.
83. In cases where engineering studies for the reference are impossible without demolition, the demolition permit is issued simultaneously with the architectural and planning assignment, before obtaining the construction permit, after paying the local fee for the demolition permit as prescribed by law to the relevant district budget.
84. If the demolition of an object does not involve the construction of a new object, and/or subsequent works do not require a construction permit, then the owner is issued a demolition permit.
85. In case of refusal of a permit, the competent authority informs the developer (owner) in writing about the reasons for the refusal.
In case of re-application and fulfillment of the requirements presented by the competent authority by the applicant, the issue of a permit or refusal is discussed within no more than 3 days.
86. If the works provided for by the permit are not started within 2 years from the date of issuance of the permit, the developer is obliged to apply to the competent authority that issued the permit to obtain additional data on possible changes in the technical conditions of development and a new permit in accordance with this procedure.
87. The developer informs the permitting authority and the State Urban Development Inspectorate of the Republic of Armenia at least 3 days before starting construction works, in accordance with Government of the Republic of Armenia 02.02.02 N91 in accordance with form No. 5 approved by the decision, unless otherwise provided for in the construction permit issued by the authorized body.
88. During construction, the developer is obliged to inform the bodies mentioned in the previous paragraph of this procedure about changes in the construction permit and the conditions specified in form No. 5 within 7 days.
89. In case of changes in design solutions in the prescribed manner, an entry is made in the construction permit in accordance with the provisions of this procedure (with the exception of the cases mentioned in the 3rd paragraph of this procedure).
CHAPTER 6 SECTION 12. PROCEDURE FOR DOCUMENTING THE COMPLETION OF CONSTRUCTION IN YEREVAN
90. The completion of construction in Yerevan is documented in accordance with the procedure established by the Government of the Republic of Armenia's decision No. 626-N of 08.05.03 "On approving the procedure for documenting the commissioning of completed construction," by drawing up a certificate of completion of construction in the form approved by the same decision, after the implementation of the construction and installation works provided for by the project, which, within 1 month of receiving a corresponding application from the developer, is certified by the signature of the Mayor of Yerevan or his deputy (Chief Architect of Yerevan) authorized by his decision, or, for cases established by law, by the head of the relevant community, and with the seal of the City Hall, and is registered in the City Hall's Department of Records Management.
91. Certificates of completion for individual buildings and structures (objects) included in a complex may be drawn up at the developer's discretion, according to their completion.
92. At the developer's discretion, the certificate of completion may be drawn up without the implementation of such works provided for by the project for which, according to the procedure approved by the Government of the Republic of Armenia's decision No. 91 of 02.02.02, a construction permit is not required.
93. The forms of objects submitted for the drawing up of the certificate of completion, as well as the executive documents, must comply with approved designs, standards, construction norms and rules.
94. The completion of buildings and structures built arbitrarily or with significant violations of design, construction norms and rules is not subject to documentation.
95. An application received for the execution of a completion act may be rejected by the Urban Development and Land Control Department of the Yerevan City Hall Staff, with the reasons and justifications for the rejection mandatory stated in the written response.
In case of a repeated application for the documentation of construction completion and the developer satisfying the previously raised requirements, the completion act is executed and handed over to the developer within 7 days.
96. The Urban Development and Land Control Department of Yerevan City Hall:
96. 1 Accepts applications addressed to the Mayor of Yerevan from developers for the execution of a completion act, to which are attached:
a/ a copy of the construction permit,
b/ copies of documents certifying the right to use the land plot (as necessary),
c/ the following executive documents for the construction of the object:
- working drawings with notes from authorized entities,
- the general logbook of construction,
- copies of acts of covered works and tests.
In the absence of the mentioned documents, if the developer has received a construction permit in the prescribed manner, they submit to the City Hall a conclusion on the technical condition of the object, issued by a person authorized to conduct technical examination or supervision, in order to document the completion of construction.
d/ the receipt for the prescribed fee for the execution of the completion act, paid to the budget of the respective district community.
96.2. Ascertains the legality and validity of the documents submitted by the developer, the compliance of the completed construction with the construction permit and the working drawings (and any changes made to them in the prescribed manner).
96.3. Ascertains the accuracy of the submitted documents' formulations, draws up a construction completion act of the appropriate form in 4 copies, and submits them within 10 days for certification by the Mayor of Yerevan or a deputy authorized by his decision (Chief Architect of Yerevan).
96.4. Formalizes the completion act, hands over one copy each to the developer, the contractor, and the relevant territorial subdivision of the State Committee of the Real Estate Cadastre of the Republic of Armenia within three days, and notifies the State Urban Development Inspectorate of this within the same period, attaching a copy of the act.
1
-
For cases defined by Article 26 of the Law of the Republic of Armenia "On Urban Development," the powers of the Urban Development and Land Control Department of Yerevan City Hall are exercised by the staff of the head of the respective district community.
-
Completion acts issued in the current quarter and their attached documents are kept in the Urban Development and Land Control Department of Yerevan City Hall. In the first month of each quarter, the completion acts of the previous quarter, with their attached documents, are handed over to the archive of the General Affairs Department of Yerevan City Hall, in the prescribed manner.
-
Completion acts issued by the head of a district community and their attached documents are registered and kept in the district administration.
-
Before submitting the construction completion act for approval, the legality of the documentation of construction completion is checked by the Legal Department of the Staff of Yerevan City Hall.
-
By order of the Mayor of Yerevan, the completion act for constructions of particular urban development and architectural significance is submitted for approval with the conclusion of the Architecture and Urban Development Department of the Staff of Yerevan City Hall.
Chapter 7
CONTROL OF URBAN DEVELOPMENT ACTIVITIES
SECTION 13. CONTROL IN LAND RELATIONS
102. According to Article 42 of the RA Land Code and Decree h.1149 of the RA Government dated November 21, 2001, the state land inspection powers in the city of Yerevan are reserved for the Mayor of Yerevan.
103. In Yerevan, the Mayor of Yerevan prevents, suspends, and eliminates illegal land use within the administrative territory of the city of Yerevan; according to Article 244.9 of the RA Code "On Administrative Offenses," the Mayor of Yerevan exercises control over the 1 purposeful use of lands and examines cases regarding administrative offenses provided for by Articles 48, 54, 54.3 of the Code (in terms of land use), Article 54.1, and Articles 56-58, imposing corresponding fines.
- According to Article 244.9 of the Code, the Mayor of Yerevan examines cases regarding administrative offenses committed in land relations by officials of district communities within the administrative boundaries of Yerevan, as well as by citizens and legal entities, and also imposes administrative penalties in the cases and manner prescribed by law.
SECTION 14. SUPERVISION OVER URBAN DEVELOPMENT ACTIVITIES
105. According to Article 26 of the RA Law "On Urban Development," the supervision of urban development activities in the city of Yerevan is carried out by the Mayor of Yerevan.
-
According to Article 26.1 of the RA Law "On Urban Development," the head of the community within the territory of a Yerevan district community prevents cases of unauthorized construction and ensures the elimination of their consequences in the manner prescribed by law, applying 1 measures of administrative responsibility in cases regarding administrative offenses provided for by Articles 154 and 154.1 of the Code.
-
According to Article 219.1 of the RA Code "On Administrative Offenses," the Mayor of Yerevan examines cases regarding the unauthorized construction of buildings and structures (Article 154 of the Code), as well as cases regarding not completing construction 1 within the timeframes prescribed by the urban development norms established for the corresponding urban development activity (Article 154 of the Code).
1
108. In 1 cases defined by Article 26 of the RA Law "On Urban Development", according to Article 219 of the RA Code "On Administrative Offenses", the head of the Yerevan district community examines cases regarding the unauthorized construction of buildings and structures.
SECTION 15. SUPERVISION IN THE FIELD OF EXTERNAL ADVERTISING
109. According to Decision N-917 of the RA Government dated October 1, 2001, the powers of the RA state administration body exercising supervision over the maintenance of legislation on advertising, in terms of external advertising in the city of Yerevan, are reserved to the Mayor of Yerevan.
CHAPTER 8 STATE URBAN DEVELOPMENT CADASTRE AND MONITORING OF URBAN DEVELOPMENT ACTIVITY
110. According to Article 20 of the RA Law "On Urban Development", the procedure established by Decision N-802 of the RA Government dated 31.12.99, and while maintaining the requirements of normative-technical documents, the management of the urban development cadastre and the monitoring of urban development activity in the city of Yerevan is performed by the Mayor of Yerevan.