Skip to main content

Collapsing step, Victory Bridge

The agency replied

Submitted on June 12, 2026

Destination: Active Citizen (Yerevan Municipality)

Tracking ID: 109307

Materials

Below is the author's own text. We publish it as filed, without edits to wording or spelling.

Ступенька отваливается, если наступить на край - может ударить по ноге
What the authorities have stated

What a body has put in writing about the problem itself: that it is there, that it is not, or that it belongs to someone else. Each statement is shown with the wording it was read from.

The problem was acknowledged on June 19, 2026.

  1. Confirms the problem is there

    Says it is theirs to deal with

    Yerevan Municipality, reply of June 19, 2026

    The authority's own wordingtranslated

  2. Confirms the problem is there

    Says it is theirs to deal with

    Yerevan Municipality, reply of July 22, 2026

    The authority's own wordingtranslated

What was promised

What the authority undertook itself — with the date it named, or without one. We keep these in view and come back to the case when a date arrives.

  1. The authority says it was not done

    finish the work — July 2026, first ten-day period

    Yerevan Municipality, reply of June 19, 2026

    The authority's own wordingtranslated

    The authority later reported it was not done

    Yerevan Municipality, message of July 22, 2026

    The authority's own wordingtranslated

    In the same message the authority promised:

  2. No date named

    finish the work — no date named

    Yerevan Municipality, reply of July 22, 2026

    The authority named no date. We come back to this promise every 30 days, next on October 18, 2026.

    The authority's own wordingtranslated

    The condition it namedtranslated

Status History

At Active Citizen (Yerevan Municipality)

  • July 22, 2026
  • Response received10:15
    Field worker 1
  • Operator's responseOperator 210:15

    Dear Citizen, we hereby inform you that the program of urgent works of the Kentron Administrative District Office has been completed; therefore, it is currently not possible to resolve the issue indicated by you. Should a new tender become available, the matter will be addressed accordingly.

    Summary

    The issue with the collapsing step and accumulated debris cannot be resolved at present because the urgent works program for the Kentron Administrative District has been completed. The matter will be addressed if a new tender becomes available.

    In this answer the authority accepted that the problem is there — it is above, under “What the authorities have stated”.

    This answer named a date — it is above, under “What was promised”.

  • June 19, 2026
  • Interim reply received10:01
    Field worker 1
  • Operator's responseOperator 110:00

    Dear Citizen, The issue you have indicated will be resolved during the first ten days of July. We will additionally inform you regarding the completion of the work.

    In this answer the authority accepted that the problem is there — it is above, under “What the authorities have stated”.

    This answer named a date — it is above, under “What was promised”.

  • June 15, 2026
  • Picked up by the addressee15:30
    Field worker 1
  • Received, awaiting processing13:45
  • Accepted. Response due by 06/18/2026, 23:59

Yerevan for People review

Submitted06/15/2026, 13:42
Submitting...06/15/2026, 13:42
Approved06/15/2026, 13:42
In Review06/12/2026, 11:06

Picked up for review

Pending Review06/12/2026, 11:01

Report submitted