Skip to main content

Need for anti-parking bollards, Yeznik Koghbatsi street 7

The agency replied

Submitted on September 3, 2026

Destination: Active Citizen (Yerevan Municipality)

Tracking ID: 128396

Materials

Below is the author's own text. We publish it as filed, without edits to wording or spelling.

Необходимо поставить анти парковочные столбики что бы авто не парковались на пешеходном переходе.

Yeznik Koghbatsi street 7, Kentron, Yerevan

40.181533, 44.510850

What was promised

What the authority undertook itself — with the date it named, or without one. We keep these in view and come back to the case when a date arrives.

  1. The date has not arrived yet

    include it in a program — 2026

    Yerevan Municipality, reply of September 9, 2026

    The authority's own wordingtranslated

  2. No date named

    consider the matter — no date named

    Yerevan Municipality, reply of September 9, 2026

    The authority named no date. We come back to this promise every 30 days, next on October 9, 2026.

    The authority's own wordingtranslated

    The condition it namedtranslated

Status History

At Active Citizen (Yerevan Municipality)

  • September 9, 2026
  • Response received13:50
    Field worker 1
  • Operator's response13:49

    Dear citizen, please be informed that according to the relevant program of the staff of the Head of Kentron administrative district, 105 yellow concrete cylinders were installed in the administrative district in 2025. According to the relevant program for 2026, 80 yellow concrete cylinders are planned to be installed in the administrative district. At the same time, please be informed that after they are installed in the already designated locations, the issue of installing yellow concrete cylinders at the address you specified will be submitted for discussion.

    Summary

    The municipality has informed that 105 concrete bollards were installed in Kentron administrative district in 2025, and another 80 are planned for 2026. However, the issue of installing concrete bollards at the specified address will only be submitted for discussion after the already planned installations are completed. No concrete timeline or confirmation for installation at this specific address has been provided.

    This answer named a date — it is above, under “What was promised”.

  • September 3, 2026
  • Picked up by the addressee13:00
    Field worker 1
  • Accepted. Response due by 09/08/2026, 23:59

Yerevan for People review

Submitted09/03/2026, 12:55
Submitting...09/03/2026, 12:55
Approved09/03/2026, 12:55
In Review09/03/2026, 12:22

Picked up for review

Pending Review09/03/2026, 11:47

Report submitted