Construction work is creating a significant amount of dust, possibly due to inadequate dust control measures. A white Jeep Renegade is parked on the street near the construction site.Yerevan MunicipalityAugust 26, 2026
- Permitted
- Deferred
- Deferred
no date namedNo date named
The condition it named— translated
The authority named no date. We come back to this promise every 30 days, next on November 24, 2026.
- No problem found
- Action against a third party
What we checked
- Part of it was done
Agency photo dated August 26, 2026, an automated reading · no person has looked yet
Status History
At Active Citizen (Yerevan Municipality)
- August 26, 2026
- Response received10:15Field worker 1
- Operator's response10:10
Dear Citizen, as a result of the inspection carried out by the employees of the Division for the Organization of Works with Communal Economy and Multi-Apartment Building Management Bodies of the Kentron administrative district head's staff, it was found that construction works at Arshakunyats Avenue Building No. 11/4, adjacent to Arshakunyats Avenue Building No. 11, are being carried out in accordance with construction permit No. ՇԹ/6/34993-26 issued by the Yerevan community on 20.08.2026. We also inform you that the construction of the building being developed, as well as its cladding, and the installation of windows and display cases, have been completed. At the current stage, landscaping works are being carried out within the construction site, which will soon be completed, and after the expiration of the construction permit, that area will also be cleared, and the delimiting fence will be removed. At the same time, we inform you that no violations of the procedure established by Yerevan City Council Decision No. 405-N dated 16.03.2012 were recorded during the inspection, and the developer was strictly warned to observe the rules of cohabitation.
- August 19, 2026
- Picked up by the addressee15:10Field worker 1
- Accepted. Response due by 08/24/2026, 23:59
Yerevan for People review
Picked up for review