Missing sidewalk behind trash bins, Nikoghayos Adonts street 3

The agency has not finished

Submitted on November 8, 2026

Destination: Active Citizen (Yerevan Municipality)

Tracking ID: 140405

Materials

Below is the author's own text. We publish it as filed, without edits to wording or spelling.

За мусорными баками отсутствуют тротуар. Необходимо расширить тротуар для прохода пешеходов.

Nikoghayos Adonts Street 3, Arabkir, Yerevan

40.210153, 44.528422

Yerevan MunicipalityNovember 9, 2026

  • Deferred

    no date namedNo date named

    The condition it named— translated

    The authority named no date. We come back to this promise every 30 days, next on December 9, 2026.

Status History

At Active Citizen (Yerevan Municipality)

  • November 9, 2026
  • Interim reply received10:55
    Field worker 1
  • Operator's response10:53

    Dear citizen, we inform you that the sidewalk improvement or new sidewalk construction works planned in the 2026 work programs of the Head of Arabkir administrative district's staff have been completed. Therefore, the issue has been inventoried and will be submitted for discussion should a similar program be available. We would also like to add that we will inform you additionally regarding the removal of solid waste.

  • November 8, 2026
  • Picked up by the addressee16:30
    Field worker 1
  • Accepted. Response due by 11/11/2026, 23:59

Yerevan for People review

Submitted11/08/2026, 16:27
Submitting...11/08/2026, 16:27
Approved11/08/2026, 16:27
In Review11/08/2026, 16:26

Picked up for review

Pending Review11/08/2026, 09:57

Report submitted