Skip to main content

Missing fenced passage to buses, Azatutyan Avenue 1

The agency replied

Submitted on September 30, 2026

Destination: Active Citizen (Yerevan Municipality)

Tracking ID: 133985

Materials

Below is the author's own text. We publish it as filed, without edits to wording or spelling.

Отсутствует огороженный проход к автобусам по дороге безопасный для пешеходов с защитой от автомобилей.

Azatutyan Avenue 1, Arabkir, Yerevan

40.199539, 44.519986

Yerevan MunicipalityNovember 10, 2026

  • Action against a third party
  • Deferred

Status History

At Active Citizen (Yerevan Municipality)

  • November 10, 2026
  • Response received15:16
    Field worker 1
  • Operator's response15:11

    Dear citizen, we inform you that construction works (construction of engineering infrastructures) were underway for the irrigation system of Azatutyan Avenue (from Yeraz Park to the sidewalk section of the Cascade stairs), however, "ART PLAS" LLC performed the works defectively, as a result of which the contract was unilaterally terminated, and a process is underway to include the mentioned company in the list of participants not having the right to participate in procurement procedures. We add that after the completion of the aforementioned process, the process of initiating construction works for the arrangement of the area will begin.

  • October 1, 2026
  • Picked up by the addressee09:35
    Field worker 1
  • September 30, 2026
  • Received, awaiting processing19:50
  • Accepted. Response due by 10/05/2026, 23:59

Yerevan for People review

Submitted09/30/2026, 19:48
Submitting...09/30/2026, 19:48
Approved09/30/2026, 19:48
In Review09/30/2026, 19:47

Picked up for review

Pending Review09/30/2026, 17:49

Report submitted