Pile of construction debris, Argishti Street 11/11
The agency has not finishedSubmitted on October 31, 2026
Destination: Active Citizen (Yerevan Municipality)
Tracking ID: 139117
Materials
Below is the author's own text. We publish it as filed, without edits to wording or spelling.
A large pile of mixed debris, including concrete chunks and other waste, is accumulated on the ground.Argishti Street 11/11, Kentron, Yerevan
40.169717, 44.503617
Yerevan MunicipalityNovember 9, 2026
- Action against a third party
- No answer on substance
no date namedNo date named
The authority named no date. We come back to this promise every 30 days, next on December 9, 2026.
Yerevan MunicipalityNovember 5, 2026
- No answer on substance
- No answer on substance
Status History
At Active Citizen (Yerevan Municipality)
- November 9, 2026
- Operator's responseOperator 211:18
Dear citizen, a letter has been sent to the owner of the territory to resolve the issue. We will inform you additionally regarding the progress of the work.
- November 5, 2026
- Interim reply received15:56Field worker 1
- Operator's responseOperator 115:55
Dear citizen, we inform you that appropriate measures are being taken to study and resolve the issue you presented. We will additionally inform you about the completion of the work.
- November 1, 2026
- Picked up by the addressee10:30Field worker 1
- Received, awaiting processing10:15
- Accepted. Response due by 11/04/2026, 23:59
Yerevan for People review
Submitted11/01/2026, 10:13
Submitting...11/01/2026, 10:12
Approved11/01/2026, 10:12
In Review11/01/2026, 10:12
Picked up for review
Pending Review10/31/2026, 18:22
Report submitted