Builders completely block the road, Verin Antarayin street 121/7
Response receivedSubmitted on May 28, 2026
Destination: Active Citizen (Yerevan Municipality)
Tracking ID: 105314
улица Верин Антараин 128/3, Кентрон, Ереван
40.194274, 44.512438
At Active Citizen (Yerevan Municipality)
- June 15, 2026
- Response received15:25Field worker 1
- June 3, 2026
- Operator's response16:44
Dear Citizen, we hereby inform you that as a result of the site inspection and study conducted by the staff of the Department for Organization of Work with Communal Economy and Multi-Apartment Building Management Bodies of the Kentron Administrative District Head's Office, it has been established that the construction works being carried out at 11 and 9 Gohar Gasparyan Street are being implemented in accordance with construction permit 01/50-02-648-24 issued by the Yerevan Municipality on 18.04.2024. We simultaneously inform you that during the site inspection the road was passable and the builder was notified of the necessity to observe cohabitation rules.
Summary
During an inspection, the road was found to be passable, and the developer was informed about the necessity to comply with coexistence regulations. The construction works are being carried out with a valid permit.
- May 29, 2026
- Picked up by the addressee13:00Field worker 1
- Received, awaiting processing12:55
- Accepted. Response due by 06/03/2026, 23:59
Yerevan for People review
Picked up for review
Report submitted