Excavated sidewalk forcing pedestrians onto road, Akhpyur Serob street 7/2
The agency repliedSubmitted on July 29, 2026
Destination: Active Citizen (Yerevan Municipality)
Tracking ID: 120356
Below is the author's own text. We publish it as filed, without edits to wording or spelling.
Тротуар раскопан ввиду чего пешеходы должны идти по проезжей части.улица Ахпюр Сероба 7/2, Арабкир, Ереван
40.196960, 44.503418
What the authority undertook itself — with the date it named, or without one. We keep these in view and come back to the case when a date arrives.
- No date named
finish the work — no date named
Yerevan Municipality, reply of August 11, 2026
The authority named no date. We come back to this promise every 30 days, next on October 18, 2026.
The authority's own wording— translated
At Active Citizen (Yerevan Municipality)
- August 11, 2026
- Response received15:00Field worker 1
- Operator's response14:59
Dear citizen, we inform you that an on-site inspection has been carried out by the employees of the Urban Development and Land Use Department of the Staff of the Head of Arabkir Administrative District. We inform you that the construction works being carried out at the given address are being performed in accordance with the approved sketch design. We would like to add that the construction works are being carried out within the boundaries defined by the project, and the sidewalk section, according to the project, is planned to be improved.
Summary
The citizen has been informed that the construction work at the address is being carried out according to an approved design. It is noted that the sidewalk section is planned to be improved as per the project. This means that the sidewalk improvement work has not yet been completed.
This answer named a date — it is above, under “What was promised”.
- July 29, 2026
- Picked up by the addressee17:30Field worker 1
- Received, awaiting processing17:25
- Accepted. Response due by 08/03/2026, 23:59
Yerevan for People review
Picked up for review
Report submitted